Wallbridge Repays Debt with Auramet and Provides Updated Production Results from Last Mill Run

February 25, 2019

Toronto, Ontario -- February 25, 2019 -- Wallbridge Mining Company Limited (TSX:WM, FWB:WC7) (“Wallbridge” or the “Company”) is pleased to announce continued positive results from ongoing development and production as part of the 35,000-tonne bulk sample at its 100%-owned Fenelon Gold Property (“Fenelon” or the “Property”).

Highlights:

  • To date approximately 25,000 tonnes of ore with a reconciled average grade of 18.19 g/t gold containing close to 14,700 ounces of gold has been processed at the Camflo Mill in four separate mill runs.
  • More than 14,000 ounces of gold have been recovered and sold
  • Stope grades are meeting expectations, ranging from 11 to 38 g/t gold (See Table 1).
  • The loan with Auramet has now been completely re-paid.

“The last press release of February 7, 2019 reported the estimated gold ounces for the 4th mill run. We are pleased to have received the final reconciliation of mill run #4 and as a result, approximately 700 more ounces than previously estimated were produced. We are currently working on the delivery of the last 10,000 tonnes to the mill for processing which should be completed in the first quarter of 2019,” stated Marz Kord, President & CEO of Wallbridge. “We are also pleased that the US $8M loan received from Auramet for the bulk sample has now been fully re-paid and we have now simplified our balance sheet.”

Fenelon Bulk Sample Production Update

Production from five stopes as well as low grade ore from a 2004 bulk sample was processed at the Camflo mill from September 2018 to January 31, 2019. Wallbridge, in its original bulk sample plans, included the historical low-grade ore as part of the first mill run while milling performance was optimized. Lessons learned from the first mill run were applied to the next mill runs to achieve remarkable recoveries of more than 98%.

Table 1. Fenelon Gold 2018/2019 Bulk Sample Summary Table to February 21, 2019
Drift/Stope material Mill Reconciled  
Tonnes  Au g/t  Contained Au Ounces  Recovered Au Ounces  Recovery  Mill Run #
2004 Ore(1) 2,277 4.23 310 248 80% 1
CH-01 Stope 4,823 16.23 2,516 2,013 80% 1 & 2
Development Ore(2) 4,615 16.12 2,392 2,375 99%  1, 2, 3, & 4
NV-01 Stope 4,852 10.55 1,646 1,636 99%  2 & 3
CH-02 Stope 1,368 18.34 807 802 99%
NV-02 Stope 2,736 18.24 1,605 1,596 99%
NV-03 Stope(2) 4,453  37.84 5,418 5,390 99% 4
Total to February 21, 2019(2) 25,124 18.19 14,693 14,061 96%  
NV-04/05 & Others(3) ~10,000 t  25-35  8,000-11,300  7,800-11,000 98% 5
Total Estimated Bulk Sample(3) ~35,000 t  20-23  23,000-26,000  22,000-25,000 98%  

(1) Ore from surface and underground stockpile left behind from the 2004 bulk sample
(2) Final reported numbers for Mill Run #4
(3) Estimated. Production of last stopes currently underway

Fenelon Geology & Exploration

The 2018 underground and surface drill programs were completed before the holidays and drill rigs were de-mobilized. Assay results of several drill holes are still pending and will be reported as they are received in the next few weeks.

The 2019 drill program (50,000-75,000 metres planned) commenced last week with the mobilization of one underground drill rig with one surface drill rig to follow at the end of the month. The 2019 underground resource drilling will initially be carried out from the recently established 5130 level (~125 m depth) and will target the main high-grade shoots down-plunge to 200 m depth.

The development of an exploration drift is currently underway and will be completed by the end of February. This drift will facilitate resource drilling to greater depth and along strike, including also the Tabasco and Cayenne mineralized corridors, as well as the new deep mineralized system discovered by the last drill hole of the 2018 program (FA-18-051, see Wallbridge Press Release dated February 21, 2019).

The 2019 surface exploration drill program will follow known mineralized zones to 300-400 m depth and test targets further away from the mine workings.

Figure 1: Fenelon Gold, 3D View

Fenelon is located in northwestern Quebec proximal to the Sunday Lake Deformation Zone ("SLDZ") which hosts the Detour Gold Mine in Ontario, and Balmoral Resources' gold deposits at Martiniere. Fenelon hosts the Discovery Zone gold deposit and surrounding 4 km strike length of a gold-hosting secondary splay of the SLDZ.

Since acquiring the property in late 2016, Wallbridge has completed an updated resource estimate and a positive pre-feasibility study on the existing resource. Wallbridge has completed successful surface exploration drilling campaigns in 2017 and in 2018 has commenced an underground 35,000-tonne bulk sample at Fenelon, which should be completed in Q1 2019. Drilling to date has significantly extended existing zones and discovered several new parallel zones. A substantial 2019 exploration and resource expansion drill program is currently underway.

The Qualified Persons responsible for the technical content of this press release are Marz Kord, P. Eng., M. Sc., MBA, President & CEO and Attila Péntek, P.Geo., Ph.D., Vice President Exploration for Wallbridge Mining Company Limited.

About Wallbridge Mining

Wallbridge is establishing a pipeline of projects that will support sustainable production and revenue as well as organic growth through exploration and scalability.

Wallbridge is currently developing its 100%-owned high-grade Fenelon Gold property in Quebec with ongoing exploration and a 35,000-tonne bulk sample. Wallbridge is also pursuing other additional advanced-stage projects which would add to the Company's near-term project pipeline. These discussions benefit from the operating capabilities Wallbridge demonstrated by safely and efficiently mining the Broken Hammer deposit in Sudbury, which was completed in October 2015. As part of this strategy, the Company recently optioned the Beschefer Project, an advanced gold property with proven size and grade-potential near Fenelon Gold. Wallbridge is also continuing partner-funded exploration on its large portfolio of nickel, copper, and PGM projects in Sudbury, Ontario, with a focus on its high-grade Parkin project.

Wallbridge also has exposure to exploration for copper and gold in Jamaica and British Columbia through its 11.3% ownership of Carube Copper Corp. (CUC:TSX-V, formerly Miocene Resources Limited, a Wallbridge spin-out of its BC assets).

For Further Information

Please visit the Company's website at www.wallbridgemining.com or contact:

Wallbridge Mining Company Limited
Marz Kord, P. Eng., M. Sc., MBA
President & CEO
Tel: (705) 682-9297 ext. 251
Email: mkord@wallbridgemining.com

Brian Penny
Chief Financial Officer
Tel: (416) 716-8346
Email: bpenny@wallbridgemining.com

This press release may contain forward-looking statements (including "forward-looking information" within the meaning of applicable Canadian securities legislation and "forward-looking statements" within the meaning of the US Private Securities Litigation Reform Act of 1995) relating to, among other things, the operations of Wallbridge and the environment in which it operates. Generally, forward-looking statements can be identified by the use of words such as "plans", "expects" or "does not expect", "is expected", "budget", "scheduled", "estimates", "forecasts", "intends", "anticipates" or "does not anticipate", or "believes", or variations of such words and phrases or statements that certain actions, events or results "may", "could", "would", "might" or "will be taken", "occur" or "be achieved". Wallbridge has relied on a number of assumptions and estimates in making such forward-looking statements, including, without limitation, the costs associated with the development and operation of its properties. Such assumptions and estimates are made in light of the trends and conditions that are considered to be relevant and reasonable based on information available and the circumstances existing at this time. A number of risk factors may cause actual results, level of activity, performance or outcomes of such exploration and/or mine development to be materially different from those expressed or implied by such forward-looking statements including, without limitation, whether such discoveries will result in commercially viable quantities of such mineralized materials, the possibility of changes to project parameters as plans continue to be refined, the ability to execute planned exploration and future drilling programs, the need for additional funding to continue exploration and development efforts, changes in general economic, market and business conditions, and those other risks set forth in Wallbridge's most recent annual information form under the heading "Risk Factors" and in its other public filings. Forward-looking statements are not guarantees of future performance and such information is inherently subject to known and unknown risks, uncertainties and other factors that are difficult to predict and may be beyond the control of Wallbridge. Although Wallbridge has attempted to identify important risks and factors that could cause actual actions, events or results to differ materially from those described in forward-looking statements, there may be other factors and risks that cause actions, events or results not to be as anticipated, estimated or intended. Consequently, undue reliance should not be placed on such forward-looking statements. In addition, all forward-looking statements in this press release are given as of the date hereof.

Wallbridge disclaims any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise, save and except as may be required by applicable securities laws. The forward-looking statements contained herein are expressly qualified by this disclaimer.

Sign Up for News


Our
Governance

boardroom icon
We believe trust and transparency are essential to the way we operate.

Join Our Team

Wallbridge Mining Company Limited is an equal opportunity employer.

Job offers at Wallbridge Mining

Position Title Status Location
Community Relations Coordinator Schedule 5-2 or 4-3 Fenelon
Environmental Coordinator Schedule 4-3 Fenelon
See All Jobs